ProjectStatus

15 July 2016

Handing over of the flats in progress

25 Apr 2016

Interior works going on in customer flats
External painting in progress
STP machinery fixing done and ready for commissioning
Plumbing water lines are connected to ring main and testing done.

31 Jul 2015

Tiles
Laying of bathroom and utility tiles in progress
Laying of floor tiles in progress

Staircase Granite laying
Completed upto Level 9 in one side
completed upto level 7, other side

Balcony grill Fitting
Completed for all units

Internal plastering
Completed upto level 8

External plastering
Completed for units 2, 3, 4, 5, 6 and 7
8 and 9 units in progress

Painting
Primer coat started for external plastering
Single coat putty work completed upto level 8

Plumbing
External vertical lines in progress

15-Jun-2015

Tiles
Laying of bathroom wall tiles in progress
Laying of floor tiles started

Staircase Granite laying
Completed upto Level 9 in one side
completed upto level 3, other side

Balcony grill Fitting
Completed for units 2, 3, 4, 5, 6 and 7
in progress for 8 and 9 units

Internal plastering
Completed upto level 8

External plastering
Completed on west side
North and south side in progress

Painting
White wash work first coat completed in Upper basement
Lower basement in progress

21-May-2015

Tiles
Laying of bathroom wall tiles started

Staircase Granite laying
Completed upto Level 9

Balcony grill Fitting
Completed for units 2, 3, 4 and 7

Internal plastering
Completed upto level 7

External plastering
Completed on west side

Painting
White wash work first coat completed in Upper basement
Lower basement in progress

20-Apr-2015

Staircase Granite laying
Completed upto Level 3

Balcony grill Fitting
Completed on west side balconies

Internal Plumbing
Completed upto Level 8

Internal Electrical Conduits
Completed upto Level 8

Painting
White wash work started in Upper basement

21-Mar-2015

Eighth Floor slab (Level 9, units – 5,6,7,8,9) completed

Internal Plastering
Completed upto Level 5
In progress in level 6 and level 7

Internal Plumbing
Completed upto Level 8

Internal Electrical Conduits
Completed upto Level 5
In progress in Level 6 and 7

Internal Painting
First coat of putty work completed upto level 5
In progress in level 6

13-Feb-2015
Internal Plastering
Completed in Level 1,2,3 and 4
In progress in level 5 and level 6

Internal Plumbing
Completed upto Level 7
In progress in Level 8

Internal Electrical Conduits
Completed upto Level 4
In progress in Level 5 and 6

Brickwork started in level 8

Internal Painting
First coat of putty work in progress upto level 4

9-Feb-2015 – Eighth Floor slab (Level 9, units – 1,2,3,4) completed

30-Dec-2014 – Seventh Floor slab (Level 8, units – 5,6,7,8,9) completed

27-Dec-2014
Internal Plastering
Completed in Level 1 and Level 3
In progress in level 2 and level 4

Internal Plumbing
Completed upto Level 6
In progress in Level 7

Internal Electrical Conduits
Completed upto Level 4
In progress in Level 5

Brickwork completed in level 7

10-Nov-2014 – Seventh Floor slab (units – 1,2,3,4) completed

07-Nov-2014 – Brickwork completed in Level 6
Electrical & Plumbing work completed in Ground and First Floor

09-Oct-2014 – Sixth Floor slab (units – 5,6,7,8,9) completed

15-sep-2014 – Brickwork commenced in Level 5

12-sep-2014 – Sixth Floor slab (units – 1,2,3,4) completed

10-sep-2014 – Brickwork completed upto level 4 (3rd floor)

26-Aug-2014 – Fifth Floor slab (units – 5,6,7,8,9) completed

11-Aug-2014 – Fifth Floor slab (units – 1,2,3,4) completed

30-Jul-2014 – Fourth Floor slab (units – 5,6,7,8,9) completed

17-Jul-2014 – Fourth Floor slab (units – 1,2,3,4) completed

29-Jun-2014 – Third Floor slab (units – 5,6,7,8,9) completed

13-Jun-2014 – Third Floor slab (units – 1,2,3,4) completed

05-June-2014 – Second Floor slab (units – 5,6,7,8,9) completed

27-May-2014 – Brick work in First floor (Level 2) commenced.

16-May-2014 – Second Floor slab (units – 1,2,3,4) completed

28-Apr-2014 – First Floor slab (units – 5,6,7,8,9) completed

21- April-2014 – Brick work in Ground floor (Level 1) commenced.

15-Apr-2014 – First Floor slab (units – 1,2,3,4) completed

17-Mar-2014 – Remaining Ground Floor slab (units – 5,6,7,8,9) completed

25-Feb-2014 – Ground Floor slab (units – 1,2,3,4) completed

05-Feb-2014 – Upper Basement Slab remaining portion completed

08-Jan-2014 – Upper Basement slab (half) completed and remaining in progress

04-Jan-2014 – Podium slab (one span) completed on West side and fully completed on North side
Lower basement Retaining wall completed (North side) and partially on West side

28-Sep-2013 – Lower Basement Slab

10-July-2013 – Plinth Beam stage

21-May-2013 – Foundation work progress

03-May-2013 – Demand note obtained for releasing the permission – Addl Com/MDP/0289/2012-13
28-Feb-2013 – Excavation Completed

25-Nov-2012 – Performed the ground breaking ceremony and started the work
10-Nov-2012 – Obtained the permission from BBMP for 50,000 Sq.ft in their zonal level
09-July-2012 – Submitted the plans to the BBMP for approval.