Project Status

20-Sep-2016

Handing over of the flats in progress
External painting work in progress

26-Apr-2016

Interior works started in customer flats
Tiles laying work in progress
External painting work in progress
Internal painting works in progress in customer flats

15-Feb-2016

Block B
Finishing works in progress

Block A
Finishing works in progress

10-Oct-2015

Block B – Wing 1
External plastering: work in progress
Painting: Putty work started in ground and first levels
Brickwork: Completed in all levels
Internal plastering: completed in all levels
Electrical: internal electrical work completed in all levels
Plumbing: Internal plumbing work completed

Block B – Wing 2
Brickwork: Completed in all levels
Internal plastering: Completed in all levels
Electrical: internal electrical work completed in all levels
Plumbing: internal electrical work completed in all levels

Block A – Wing1
Slabs: completed in all levels
Brickwork: Fourth level in progress
Electrical: internal electrical work in progress
Plumbing: In progress in level 2 (first floor)

Block A – Wing 2
Slabs: completed upto level 4 (third floor roof slab)
Brickwork: Level 3 in progress
Electrical: internal electrical work in progress
Plumbing: In progress in level 2

02-Sep-2015

Block B – Wing 1
Brickwork: Completed in all levels
Internal plastering: completed upto level 3 (second floor)
Electrical: level 5 in progress
Plumbing: Internal plumbing work completed

Block B – Wing 2
Brickwork: Level 5 in progress
Internal plastering: second floor units in progress
Electrical: In progress in level 4
Plumbing: In progress in level 4

Block A – Wing1
Slabs: completed upto level 4 (third floor roof slab)
Brickwork: completed upto first floor. Second floor in progress
Plumbing: In progress in level 2 (first floor)

Block A – Wing 2
Slabs: completed upto level 4 (third floor roof slab)
Brickwork: commenced upto first floor
Plumbing: In progress in level 1

31-July-2015

Block B – Wing 1
Brickwork: Completed in all levels
Internal plastering: ground floor completed and Commenced in level 2 (First Floor)
Electrical: In progress in level 4
Plumbing: Plumbing work completed upto level 4

Block B – Wing 2
Brickwork: Level 5 in progress
Internal plastering: ground floor duplex units in progress
Electrical: In progress in level 3
Plumbing: In progress in level 3

Block A – Wing1
Brickwork: completed in ground floor and started in first floor

Block A – Wing 2
Slabs: completed upto level 3 (second floor roof slab)
Brickwork: commenced in ground floor

04-July-2015

Block B – Wing 1
Brickwork: Completed upto level 4 and commenced in level 5

Internal plastering: Commenced in level 1 (Ground Floor)

Electrical: In progress in level 3
Plumbing: Plumbing work completed upto level 3

Block B – Wing 2
Brickwork: Completed upto level 3 and level 4 in progress

Electrical: In progress in level 3
Plumbing: Plumbing work completed upto level 2

Block A – Wing1
Level 3 (Second floor roof slab) completed
Brickwork: Completed in level 1

Block A – Wing2
Level 2 (First floor roof slab) completed

20-Apr-2015

Block B – Wing 1
Terrace Slab completed
Brickwork commenced in Second Floor

Block B – Wing 2
Brickwork completed in Ground Floor
Brickwork commenced in First and Second Floor

Block A – Wing1
First Floor slab centering work in progress

Blcok A – wing2
Upper basement slab completed.
Ground floor centering work in progress

24-Mar-2015 – ‘Block – B’ wing2 Third floor slab completed

11-Mar-2015 -
Block – A wing1 Ground floor slab completed
Block B – Wing1 – Brick work commenced in Ground and First floor
Block B – Wing2 – Brick work commenced in Ground floor

09-Feb-2015 – ‘Block – B’ wing2 Second floor slab completed

19-Jan-2015 – ‘Block – A’ wing1 upper basement slab completed

19-Dec-2014 – ‘Block – B’ wing2 First floor slab completed

17-Dec-2014 – ‘Block – A” wing2 Lower basement slab completed

21-Nov-2014 – ‘Block – B’ wing1 Third floor slab completed

25-Oct-2014 – ‘Block – A” Lower basement slab completed in Wing1

22-Sep-2014 – ‘Block – B” wing2 ground floor brick work commenced

23-Sep-2014 – ‘Block – B’ wing1 Second floor slab completed

15-Sep-2014 – ‘Block – B” wing1 ground floor brick work commenced

23-Aug-2014 – ‘Block – B’ wing1 First floor slab completed

20-Aug-2014 – ‘Block – B’ wing2 Ground floor slab (half) completed

01-Aug-2014 – ‘Block – B’ wing2 parking slab (remaining half) completed

23-Jul-2014 – ‘Block – B’ wing1 ground floor slab completed

30-Jun-2014 – ‘Block – B’ wing2 parking slab (half) completed

20-May-2014 – ‘Block – A’ Wing1 foundations completed

5-Apr-2014 – ‘Block – B’ Wing1 slab completed and Block-A foundations under progress

22-Mar-2014 – ‘Block – B’ Wing1 Centering work completed
Wing2 Columns under progress

05-Jan-2014 – ‘Block – A’ earthwork excavation commenced
01-Jan-2014 – ‘BLock – B’ plinth beam work under progress
23-Aug-2013 – ‘Block – B’ earth work commenced
09-Aug-2013 – Site handed over and Work commenced at site
30-May-2013 – Obtained all approval from BBMP wide no – BBMP/Addl.Dir/JD NORTH/LP/0381/2012-13
25-Apr-2013 – Persuing to obtain the “IGBC Green Homes – Silver” rating from IGBC (Indian Green Building Council)
27-Mar-2013 – The drawings are re-submitted to BBMP for approval
Getting ready to submit the plans to BBMP for approval.
21-Nov-2012 – BWSSB NOC received
The concept and the building drawings are finalized.